Jan 2021 – May 2021

PROVISION OF CIVIL INFRASTRUCTURE WORK

Contractual: ANTONOIL SERVICES DMCC
Beneficiary/Employer: BOC / Basra, Iraq
Period: Jan 2021 – May 2021
Value: USD 4,293,315

 

Scope of work

• Scraping for the existing Asphalt Road and
subgrade compaction (500 mm deep).
• Soil Backfilling with compaction 3 layers (250 mm
each layer; total 750 mm).
• Subbase backfilling with compaction 1st layer
250 mm
• Subbase backfilling with compaction 2nd
layer 250 mm.
• Subbase backfilling with compaction for
shoulders.

• Crushed stone backfilling 150 m thick,
width=7m.
• Asphalt paving marking (3 lines).
• Construction of 3 reinforced concrete
culverts.
• Asphalt paving 100 mm thick.

 